Feed-In-Tariffs Amendments [UK]

This is the Feed-In-Tariffs (Amendment) Order 2016 (S.I. 2016 No. 319) (“the 2016 Order”) that came into force on 31st March 2016.

The 2016 Order corrects amendments made to the Feed-in-Tariffs Order 2012 (“2012 Order”) by the Feed-In-Tariffs (Amendment) (No.3) Order.

Feed-In-Tariffs-uk

The main changes the 2016 Order implements are under Article 4 which states it amends the following articles of the 2012 Order:

  • article 4 (application of this Chapter) to insert a cut-off date of 31st March 2016 so that “excluded transitional applications” made after that date can no longer be accredited. An excluded transitional installation is one that would fall into the definition of transitional installation within the meaning of article 8D(1)(b) had it been made between 15th January and 31st March 2016;
  • article 8B (the application limit), paragraph (4)(a)(ii) so that for the purposes of article 8B and 8C (the application limit: adjustments), an application is treated as being received by the Authority in respect of an eligible installation that uses an MCS-FIT technology at the point that the MCS certificate is issued, even if no application is actually made for that installation;
  • article 8D (transitional installations), paragraph (1)(b) so that an application for a community energy installation that has been pre-registered under article 11 of the 2012 Order (pre-registration of community energy installations) or a school installation under article 12 of the 2012 Order (pre-registration of school installations), are not transitional installations;
  • article 9 (preliminary accreditation), paragraphs (8) and (8A) so that the expression “treated as being received by the Authority” is inserted into those paragraphs with the meaning set out in article 8B(4)(a);
  • article 10 (effect of preliminary accreditation), paragraph (3)(b) so that the tariff date for an installation with preliminary accreditation is the later of either the date on which the application is received by the Authority or the beginning of the tariff period in which the application qualifies for accreditation; and
  • article 10(4) so that a commissioned installation is materially different to the one for which preliminary accreditation was granted if, among other things, its total installed capacity is greater, or if it has been reduced to the extent that it would have been eligible for a different generation tariff.

For more detailed information and the complete alterations made by the 2016 Order refer directly to the legislation instrument.

A full impact assessment is available on the legislation.gov.uk website.

Sources:

Feed-In-Tariffs (Amendment) Order 2016 (S.I. 2016 No. 319) published on legislation.gov.uk on 10th March 2016.

Our EHS experts are at your disposal and will be happy to answer your questions.

join us on linkedin

We invite you to subscribe to our newsletter.

On the same subject